Metallurgical
Plant Start-Up and Commissioning

Performance
Associates' on-site start-up coordinator provides the link
between your operation's personnel and the construction contractor's
personnel during the critical preoperational testing phase.
The key to Performance Associates' approach is a PC database
which tracks the entire start-up program. Literally thousands
of transactions must be tracked and retrieved as necessary
during preoperational testing. Diverse activities such as pipe
flushing, motor grounding and bumping, and loop testing all
must be tracked, any discrepancies noted, and corrective work
scheduled. Reports must be generated by the system indicating
the status of the entire preoperational testing program. Performance
Associates' start-up specialists are experienced managers having
extensive experience with metallurgical plant operations and
maintenance. Our PC based start-up database application includes
the following functions:
- Pipe
tracking by P&ID, package number, and area, including
connections, flushing, pressure test, specification check,
and support check.
- Equipment
tracking by P&ID, package number, and area, including
cleaning, drive alignment, drive belts, guards, interlocks
check, lubrication complete, mounting, packing or seals
installed, pressure test, rotation check, and specifications
check as applicable.
- Motor
tracking by area and equipment, including megger test,
raceway check, motor setting, conduit check, power wiring
terminations, control wiring complete, logic check, overloads
installed, bump and run, and data sheet complete.
- Instruments
by P&ID, package number, and area, including calibration,
piping check, installation check, wiring complete, and
loop test.
- Punch
list tracking by area and equipment or pipe number, including
date logged, description, date scheduled for correction,
who is responsible, and date corrected.
-
Notes
to allow tracking of critical issues by equipment number
or piping.
Following
completion of equipment and instrument preoperational tests, complete
packages, such as the air system, steam system, or crushing system
can be functionally tested as a system to ensure everything in
the system works together as necessary before introduction of
feed. |